Construction Schedule
Construction Schedule Summary
By ISBS GROUP
Mar 6, 2005, 20:41

Please find below the main Construction Schedule for the New Building.
The first Column is the work category and the second is the original date of completion.

SITEWORK

 

Demolition

3/7/2005

Grading

4/16/2005

Underground Utilties

4/22/2005

Concrete

4/25/2005

Paving

7/29/2005

Other

9/18/2005

Landscaping

9/9/2005

 

 

 

 

BUILDING

 

Concrete

5/9/2005

Masonry

5/10/2005

Metals

6/15/2005

Wood & Plastics

6/27/2005

Thermal

7/25/2005

Doors & Windows

8/15/2005

Finishes

9/19/2005

Specialties

9/15/2005

Equipment

9/25/2005

Furnishing

10/19/2005

Special Construction

10/9/2005

Fire Protection

10/9/2005

Plumbing

9/29/2005

HVAC

10/6/2005

Electrical

9/25/2005

 